Contents
Executive
Summary
1.1 Purpose of the Report
1.2 Structure of the Report
2.1 Background
2.2 General Site Description
2.3 Construction Activities
2.4 Project Organisation and
Management Structure
2.5 Status of Environmental
Approval Documents
3 Environmental Monitoring Requirements, environmental
Mitigation Measures
4 Implementation Status on Environmental Protection
Requirements
6.1 Weekly Site Audits
6.2 Landscape and Visual Audit
7 Environmental Non-conformance
7.1 Summary of Environmental
Non-Compliance
7.2 Summary of Environmental
Complaint
7.3 Summary of Environmental
Summon and Successful Prosecution
8.1 Key Issues for the Coming
Month
8.2 Construction Programme
LIST OF TABLES
Table 2.1 Summary of Activities Undertaken in the Reporting
Period
Table 2.2 Summary of Environmental Licensing, Notification and
Permit Status
Table 5.1 Quantities of Waste Generated from the Project
Table 8.1 Works to be undertaken in the Next Reporting Period
LIST OF ANNEXES
Annex A |
|
Annex B |
|
Annex C |
|
Annex D |
|
Annex E |
|
Annex F |
|
Annex G |
Environmental complaint,
Environmental Summons and Prosecution Log |
Annex h |
|
|
|
EXECUTIVE SUMMARY
The construction works of No. EP/SP/61/10 Organic Resources
Recovery Centre Phase 1 (the Project) commenced
on 21 May 2015. This is the 45th
monthly Environmental Monitoring and Audit (EM&A) report presenting the
EM&A works carried out during the period from 1 to 28 February 2019 in accordance
with the EM&A Manual.
Summary of Works undertaken during the Reporting Month
Works undertaken in the reporting month included:
·
Systems being operated – waste reception,
pre-treatment, CAPCS extraction, the digesters, the centrifuge, the desulphurisation,
the emergency flare, the CHPs, the ASP and the biological wastewater treatment
plant; and
·
Process commissioning in progress, operations included
waste reception, pre-treatment, CAPCS extraction, the digesters, the
centrifuge, the composting tunnels, the desulphurisation, the emergency flare,
the CHPs, the ASP and the biological waste water treatment plant (about 110-130t/d
SSOW input).
Environmental Monitoring and Audit Progress
A
summary of the monitoring activities undertaken in this reporting period is
listed below:
·
Joint Environmental Site Inspections |
5 times |
·
Landscape & Visual Inspections |
3 times |
Odour
Odour patrol were conducted by representatives of the
Contractor, the ER and Employer (EPD Project Team) on 1, 4, 8, 9, 11, 13, 15, 20, 22, 25 and 27 February 2019. The Independent Odour Patrol Team, ALS
Technichem (HK) Pty Ltd (ALS), has also joined the odour patrol on 20 February
2019. No Level 2 Odour Intensity was
recorded during odour patrols.
No air sample was collected during this reporting
period.
Waste Management
Waste generated from this Project includes inert
construction and demolition (C&D) materials (public fill) and non-inert
C&D materials (construction wastes).
Inert C&D materials (public fill) include bricks,
concrete, building debris, rubble and excavated spoil. In total, 0.00 tonnes of
inert C&D material were generated from the Project.
Non-inert C&D materials (construction wastes)
include metals, paper / cardboard packaging waste, plastics and other wastes
such as general refuse. 0.00 kg of
metals, 0.00 kg of papers/ cardboard packing and 0.00 kg of plastics were sent
to recyclers for recycling during the reporting period. 26.69 tonnes of general refuse was disposed of
at the landfill.
0.00 L of chemical waste was collected by licenced
waste collector.
Environmental Site Inspection
Five weekly joint environmental site inspections were
carried out by the representatives of the Contractor and the ET. The IEC was also present at the joint inspection on 22 February 2019. Details of the audit findings and
implementation status of the mitigation measures are presented in Section 6.1.
Landscape & Visual
On-site inspections on landscape and visual
mitigation measures were performed on 1, 15 and 26 February 2019. Details of the audit findings and
implementation status of the mitigation measures are presented in Sections 6.2.
Environmental
Exceedance/Non-conformance/Compliant/Summons and Prosecution
No exceedance was
recorded during the reporting period.
No incident
occurred during the reporting period.
No complaint/ summon/prosecution was received in this
reporting period.
Future Key Issues
Works to be undertaken in the next reporting month
include:
·
Continue
testing and process commissioning works.
ERM-Hong Kong, Limited (ERM) was appointed by OSCAR
Bioenergy Joint Venture (the Contractor) as the Environmental Team (ET) to
undertake the Environmental Monitoring and Audit (EM&A) programme for the Contract
No. EP/SP/61/10 of Organic Waste Treatment Facilities Phase I, which
the project name has been updated to Organic Resources Recovery Centre (Phase I)
(the Project)
since November 2017.
This is the 45th EM&A report which summarises
the monitoring results and audit findings for the EM&A programme during the
reporting period from 1 to 28 February 2019.
The structure of the report is as follows:
Section 1: Introduction
It details the scope and structure of the report.
Section 2: Project
Information
It summarises the background and
scope of the Project, site description, project organization, construction
programme, activities undertaken and status of the Environmental Permits
(EP)/licences.
Section 3: Environmental Monitoring Requirements
It summarises the environmental monitoring
requirements including monitoring parameters, programmes, methodologies,
frequency, locations, Action and Limit Levels, Event/Action Plans,
environmental mitigation measures as recommended in the EM&A Manual and
approved EIA report.
Section 4: Implementation Status on
Environmental Mitigation Measures
It summarises the implementation of environmental
protection measures during the reporting period.
Section 5: Waste Management
It summarises the quantity of public fill and
construction waste generated in the reporting period
Section 6: Environmental Site
Inspection
It summarises the audit findings of the weekly site
inspections undertaken within the reporting period.
Section 7: Environmental
Non-conformance
It summarises any exceedance of environmental
performance standard, environmental complaints and summons received within the
reporting period.
Section 8: Further Key Issues
It summarises the impact forecast for the next
reporting month.
Section 9: Conclusions
The Organic
Resources Recovery Centre (ORRC) Phase I development (hereinafter referred to
as “the Project”) is to design, construct and operate a biological treatment
facility with a capacity of about 200 tonnes per day and convert
source-separated organic waste from commercial and industrial sectors (mostly
food waste) into compost and biogas through proven biological treatment
technologies.
The environmental acceptability of the construction and operation
of the Project had been confirmed by findings of the associated Environmental
Impact Assessment (EIA) Study completed in 2009. The Director of Environmental Protection
approved this EIA Report under the Environmental Impact Assessment Ordinance
(EIAO) (Cap. 499) in February 2010 (Register No.: AEIAR-149/2010)
(hereafter referred to as the approved EIA Report). Subsequent Report on Re-assessment on
Environmental Implications and Report on Re-assessment on Hazard to Life
Implications were completed in 2013, respectively.
An Environmental Permit (EP) (No. EP-395/2010)
was issued by the Environmental Protection Department (EPD) to the EPD, the
Permit Holder, on 21 June 2010 and varied on 18 March 2013 (No. EP-395/2010/A)
and 21 May 2013 (No. EP-395/2010/B), respectively. The Design Build and Operate Contract for the
ORRC Phase 1 (Contract No. EP/SP/61/10 Organic Resources Recovery Centre (Phase
1) (the Contract)) was awarded to SITA Waste Services Limited, ATAL Engineering
Limited and Ros-Roca, Sociedad Anonima jointly trading as the OSCAR Bioenergy
Joint Venture (OSCAR or the Contractor).
A Further EP (No. FEP-01/395/2010/B) was issued by the EPD to the OSCAR
on 16 February 2015. Variation to both EPs
No. EP-395/2010/B and No. FEP-01/395/2010/B were made in December 2015. The latest EPs, No. EP-395/2010/C and No.
FEP-01/395/2010/C, were issued by the EPD on 21 December 2015.
Under the requirements of Condition 5 of the EP (No.
FEP-01/395/2010/C), an Environmental Monitoring and Audit (EM&A) programme
as set out in the Agreement No. CE7/2008 (EP) EM&A Manual (hereinafter
referred to as EM&A Manual) is required to be implemented. ERM-Hong Kong, Ltd (ERM) has been appointed
by OSCAR as the Environmental Team (ET) to undertake the EM&A programme
for the Contract.
The construction works commenced on 21 May 2015. Substantial completion of the construction
works was confirmed on 3 December 2018.
However, the construction phase of the EM&A programme has not been
terminated as testing and commissioning is in progress.
The
Project Site is located at Siu Ho Wan in North Lantau with an area of about 2
hectares. The layout of
the Project Site is illustrated in Annex A.
A summary of the major activities undertaken in the reporting
period is shown in Table 2.1. The site layout plan is shown in Annex
B. The construction programme of the Project is
presented in Annex C.
Table
2.1 Summary of
Activities Undertaken in the Reporting Period
Activities Undertaken in the Reporting Period |
·
Systems being operated – waste reception,
pre-treatment, CAPCS extraction, the digesters, the centrifuge, the
desulphurization, the emergency flare, the CHPs, the ASP and the biological
waste water treatment plant; ·
Process commissioning in progress - waste reception,
pre-treatment, CAPCS extraction, the digesters, the centrifuge, the
composting tunnels, the desulphurisation, the emergency flare, the CHPs, the
ASP and the biological waste water treatment plant (about 110-130 t/d SSOW input). |
The project organisation chart and contact details are
shown in Annex D.
A summary of the valid permits, licences, and/or
notifications on environmental protection for this Project is presented in Table 2.2.
Table
2.2 Summary of Environmental Licensing,
Notification and Permit Status
Permit/ Licences/ Notification |
Reference |
Validity Period |
Remarks |
Environmental Permit |
FEP-01/395/2010/C |
Throughout the Contract |
Permit granted on 21 December
2015 |
Notification of Construction
Works under the Air Pollution Control (Construction Dust) Regulation |
Ref No. 386715 |
Throughout the Contract |
- |
Effluent Discharge License |
WT00024352-2016 |
3 June 2016 – 30 June 2021 |
Approved on 3 June 2016 |
Construction Noise Permit –
P1&P2 |
GW-RW0538-18 (Superseded
CNP GW-RW0229-18) |
21
January 2019-20 July 2019 |
Approved
on 31 December 2018 |
Construction Noise Permit – P5
(slope) |
GW-RW0347-18
(superseded the GW-RW0107-18) |
30
September 2018 – 29 March 2019 |
Approved
on 15 August 2018 |
Chemical Waste Producer
Registration |
WPN 5213-961-O2231-01 |
Throughout the Contract |
Approved on 29 April 2015 |
Waste Disposal Billing Account |
Account number: 702310 |
Throughout the Contract |
- |
All
the relevant environmental mitigation measures listed in the approved EIA
Report and EM&A Manual are summarised in Annex E.
According to the EM&A Manual and EP requirements,
no air quality, noise and water quality monitoring is required during the
construction phase.
According to the EM&A Manual and EP requirements,
odour monitoring is required during the commissioning phase.
The odour patrols shall be conducted by an odour
patrol team. The odour patrol team will patrol and sniff along an odour patrol
route at the site boundary. The implementation of the odour patrol shall be
subject to the prevailing weather forecast condition and no odour patrol should
be carried out during rainy day. The
odour patrol team should be comprised of at least two independent trained
personnel / competent persons, who should pass a set of screening tests.
Odour patrols were conducted by representatives of the Contractor,
the ER and Employer (EPD Project Team) on 1, 4, 8, 9, 11, 13, 15, 20, 22, 25
and 27 February 2019. The Independent
Odour Patrol Team, ALS Technichem (HK) Pty Ltd (ALS), has also joined the odour
patrol on 20 February 2019. According
to the EM&A Manual and EP requirements, it is considered an exceedance if the odour intensity
recorded by the panellists is Level 2 or above. During this reporting period, no Level 2 Odour
Intensity was recorded. The odour patrol
results are shown in Annex H.
No air sample was
collected during this reporting period.
Bi-weekly landscape and visual audit is required to ensure that the design,
implementation and maintenance of landscape and visual mitigation measures
recommended in the approved EIA Report are fully achieved.
The Contractor
has implemented environmental mitigation measures and requirements as stated in
the approved EIA Report and EM&A Manual.
The implementation status of the measures during the reporting period is
summarised in Annex E.
Wastes generated from this Project include inert
construction and demolition (C&D) materials (public fill) and non-inert
C&D materials (construction waste). Construction
waste comprises general refuse, metals and paper/cardboard packaging
materials. Metals generated from the Project
are also grouped into construction waste as the materials were not disposed of
with others at public fill. Reference
has been made to the Monthly Summary Waste Flow Table prepared by the
Contractor (see Annex F). With reference to the relevant handling
records and trip tickets of this Project, the quantities of different types of
waste generated in the reporting month are summarised in Table 5.1.
Table 5.1 Quantities
of Waste Generated from the Project
Month / Year |
Quantity |
|||
|
Total Inert C&D Materials Generated (a) |
Non-inert C&D Materials (b) |
||
C&D Materials Recycled (c) |
C&D Waste Disposed of at Landfill (d) |
Chemical Waste |
||
January 2019 |
0.00 tonnes |
0.00 kg |
26.69 tonnes |
0.00 L |
Notes: (a) Inert
C&D materials (public fill) include bricks, concrete, building debris,
rubble and excavated spoil. In total, 0.00 tonnes
of inert C&D material were generated from the Project. The detailed waste flow is presented in Annex F. (b) Non-inert
C&D materials (construction wastes) include metals, paper / cardboard
packaging waste, plastics and other wastes such as general refuse. Metals generated from the Project were grouped
into construction wastes as the materials were not disposed of with others at
the public fill. (c) 0.00
kg of metals, 0.00 kg of papers/ cardboard packing and 0.00 kg of
plastics were sent to recyclers for recycling during the
reporting period. (d) Construction wastes other than
metals, paper/cardboard packaging, plastics and chemicals were disposed of at
NENT Landfill by subcontractors. |
Joint
site inspections were conducted by representatives of the Contractor, the ER,
IC and the ET on 1, 8, 15, 22 and 26 February 2019. The IEC was also
present at the joint inspection on
22 February 2019. Follow-up actions resulting
from the last site inspections were generally taken as reported by the
Contractor.
Key observations
during the reporting period are summarised as follows:
1
February 2019
·
Chemical drums were observed near Building 2 and
the contractor was advised to provide drip trays to the chemical drums or
replace the drums to designed storage area according to the Code of Practice.
·
Construction parts were observed next to Building 2
and the contractor was advised to remove or store the parts properly to avoid
stockpile of parts outdoor.
8 February 2019
·
Chemical drums were observed near Building 2 and
the contractor was advised to provide drip trays to the chemical drums or
replace the drums to designed storage area according to the Code of Practice.
·
Construction parts were observed next to Building 2
and the contractor was advised to remove or store the parts properly to avoid
stockpile of parts outdoor.
15 February 2019
·
Chemical drums were observed near Building 2 and
the contractor was advised to provide drip trays to the chemical drums or
replace the drums to designed storage area according to the Code of Practice.
·
Construction parts were observed next to Building 2
and the contractor was advised to remove or store the parts properly to avoid stockpile
of parts outdoor.
22 February 2019
·
Chemical drums were observed near Building 2 and
the contractor was advised to provide drip trays to the chemical drums or
replace the drums to designed storage area according to the Code of Practice.
26 February 2019
·
Chemical drums were observed near Building 2 and
the contractor was advised to provide drip trays to the chemical drums or
replace the drums to designed storage area according to the Code of Practice.
In accordance with the EM&A Manual, bi-weekly landscape and
visual inspection is required to
ensure that the design, implementation and maintenance of landscape and visual
mitigation measures recommended in the EIA Report are fully achieved. On-site inspections of the landscape and
visual mitigation measures were performed on 1, 15 and 26 February 2019.
It was confirmed that the necessary landscape and visual mitigation measures
as summarised in Annex E were generally implemented
by the Contractor. No specific observation was found during site
inspections on 1, 15 and 26 February 2019.
No non-compliance event was received during the
reporting period.
Works to be undertaken for the coming reporting period
are summarised in Table 8.1.
Table 8.1 Works to
be undertaken in the Next Reporting Period
Activities
in the Next Reporting Period |
·
Continue the testing and process commissioning works. |
Only testing and process commissioning works are
expected in the next reporting period. No major construction activities have
been scheduled in March 2019 and hence no potential environmental impacts are
expected.
The most up-to-date construction programme for the
Project is presented in Annex C.
This EM&A Report presents the EM&A programme undertaken
during the reporting period from 1 to 28 February 2019 in accordance with
EM&A Manual and requirements of EP (FEP-01/395/2010/C).
No air quality, noise and water quality monitoring is
required during the construction phase.
Odour patrols and monitoring are required during the
commissioning phase. No exceedance of
odour intensity limit for all odour patrol events. No air sample was collected during this
reporting period.
Bi-weekly landscape
and visual monitoring was conducted in the reporting period. The necessary landscape and visual mitigation
measures recommended in the approved EIA Report were generally implemented by
the Contractor.
No incident occurred during reporting period.
No complaint/summon/prosecution was received.